10 May 2017  The Rostov NPP Information and Public Relations Administration
Rostov NPP: the readiness of starting power unit No 4 turbine is 90%
The turbine assembly is almost completed at the fourth power unit of Rostov NPP. According to the Chief Engineer of VdMU LLC Viktor Sivolapov – the representative of the organization that assembles the turbine room equipment – the readiness of the turbine is 90%. The closing of high-pressure cylinder with protection cap is one of the final operations before placing the turbine generator on the turning gear.
4 May 2017  Information and Public Relations Administration Rosenergoatom Concern JSC
Rosenergoatom: in April electric energy generation of Russian NPPs rose by 8.85%
In April, 2017 Russian NPPs (branches of Rosenergoatom Concern) increased the total electric energy generation by 8.85% compared to the same period in 2016.
4 May 2017  Leningrad NPP Information and Public Relations Administration
The specialists of Leningrad NPP have started testing the reactor building inner containment dome at power unit No 1 under construction
At Leningrad NPP’s power unit No 1 under construction the specialists have proceeded to one of the main stages of the commissioning works – the testing of the reactor building’s leak-tight enclosure system.
4 May 2017  Novovoronezh NPP Information and Public Relations Administration
35 students from Turkey have completed their training at Novovoronezh NPP
At Novovoronezh NPP 35 Turkish fifth-year students from Obninsk institute of MEPhI National Research Nuclear University (MEPhI NRNU) have completed their work experience internship.
3 May 2017  Center for Energy Expertise
The WANO Chairman Jacques Regaldo greets participants of the ATOMEXPO-2017 International Forum
According to Atomexpo LLC Press Service, The Chairman of the World Association of Nuclear Operators (WANO), Jacques Regaldo, has sent a message of greetings to the participants of the IX ATOMEXPO-2017 International Forum, which will be held on 19-21 June, 2017 in Moscow at the site of Gostinniy Dvor exhibition complex.
2 May 2017  The Rostov NPP Information and Public Relations Administration
Rostov NPP: the specialists of the starting power unit No 4 have begun the reactor assembly
The specialists of the Centralized Repair Shop (CRS) of Rostov NPP together with Sezam JSC contractors have started the assembly of the 4th power unit’s reactor.
28 April 2017  Leningrad NPP Information and Public Relations Administration
Leningrad NPP: the first of four diesel generators of power unit No 1 under construction is run at idle
At the power unit No 1 of Leningrad NPP the full-scale commissioning of the emergency power system’s process equipment is in process: the first set diesel generator of the reserve diesel power plant is run at idle. The commissioning is the first stage of putting the diesel power plant into operation that is preceded by the equipment designing, delivery, construction and installation works, and connection to the network.
28 April 2017  Leningrad NPP Information and Public Relations Administration
The assembly of the compressor station equipment of Leningrad NPP’s power unit No 1 under construction is completed
In the combined gas building of VVER-1200 type power unit No 1 under construction the assembly of the plantwide compressor station process equipment is completed. In the nearest future the facility will be connected to a voltage that in turn will give a start for carrying out of the full-scale commissioning works on this equipment.
28 April 2017  Kursk NPP Information and Public Relations Administration
The WANO technical support mission’s examining of the performance indicators has finished its work at Kursk NPP
On 24-28 April, 2017, upon the request of Kursk NPP the technical support mission of the WANO MC studying the System of the NPP Performance Indicators (PI) worked at the nuclear power plant.
26 April 2017  Kursk NPP Information and Public Relations Administration
A Project Office was established at Kursk NPP-2 to effectively manage the construction of the replacement plant
To effectively and flexibly manage the construction of the power units No 1 and 2 at the site of Kursk NPP-2 replacement plant, the “Achieving the key event of ‘initial concrete’ during the construction of Kursk NPP-2” Project Office was established.