10 August 2018  THE INFORMATION AND PUBLIC RELATION DEPARTMENT OF NOVOVORONEZH NPP
At the power unit No 2 of Novovoronezh NPP-2 under construction the hydraulic testing of the secondary circuit on consistency and strength is completed
At the power unit No 2 of Novovoronezh NPP-2 under construction the hydraulic testing of the secondary circuit on consistency and strength is completed
On 10 August, 2018 at 13:40 during the cold and hot trial (CHT) stage of the equipment at the power unit No 2 of Novovoronezh NPP-2 (No 7 of NVNPP) the hydraulic testing of the secondary circuit on consistency and strength was successfully completed.

9 August 2018  KURSK NPP INFORMATION AND PUBLIC RELATIONS ADMINISTRATION
“It is planned to place reactor vessel of the power unit No 1 of Kursk NPP-2 at its proper location in 2020”, Andrey Petrov, the Head of Rosenergoatom
“It is planned to place reactor vessel of the power unit No 1 of Kursk NPP-2 at its proper location in 2020”, Andrey Petrov, the Head of Rosenergoatom
The reactor vessel of the VVER-TOI power unit No 1 of Kursk NPP-2 is planned to be placed at its proper location in 2020. It was told by the Director General of Rosenergoatom JSC (a part of Rosatom’s Electric Energy Division) Andrey Petrov during the working trip to Kurchatov (Kursk Oblast).

9 August 2018  THE INFORMATION AND PUBLIC RELATION DEPARTMENT OF NOVOVORONEZH NPP
At Novovoronezh NPP the international experts of the WANO completed their work within the support mission and preliminary visit of the Pre-Startup Peer Review
At Novovoronezh NPP the international experts of the WANO completed their work within the support mission and preliminary visit of the Pre-Startup Peer Review
On 10 August, 2018 at 13:40 during the cold and hot trial (CHT) stage of the equipment at the power unit No 2 of Novovoronezh NPP-2 (No 7 of NVNPP) the hydraulic testing of the secondary circuit on consistency and strength was successfully completed.

7 August 2018  INFORMATION AND PUBLIC RELATIONS DEPARTMENT OF LENINGRAD NPP
The final 15-day testing of the VVER-1200 innovative power unit No 1 has started at Leningrad NPP
The final 15-day testing of the VVER-1200 innovative power unit No 1 has started at Leningrad NPP
At Leningrad NPP, a complex testing of the innovative generation 3+ power unit No 1 with VVER-1200 reactor has begun. Within 15 days the power unit will operate in a continuous mode at 100% power. The testing should confirm the stability of joint operation of the unit’s main and auxiliary equipment, and automatic process control systems.

6 August 2018  INFORMATION AND PUBLIC RELATIONS DEPARTMENT OF LENINGRAD NPP
Leningrad NPP: the assembly of the turbine island main equipment has been completed at the construction site of the innovative power unit No 2
Leningrad NPP: the assembly of the turbine island main equipment has been completed at the construction site of the innovative power unit No 2
At the construction site of the innovative power unit No 2 with the VVER-1200 reactor of Leningrad NPP, the specialists completed the assembly of all the main equipment of the turbine building. The work inside the turbine building is conducted according to the schedule.

6 August 2018  INFORMATION AND PUBLIC RELATIONS DEPARTMENT OF LENINGRAD NPP
The personnel of the Finnish Hanhikivi-1 NPP will undergo an internship at Leningrad NPP
The personnel of the Finnish Hanhikivi-1 NPP will undergo an internship at Leningrad NPP
Instructors of Fennovoima Oy (Finland) visited the Training Department (TD) of Leningrad NPP. The Finnish guests learned how to train operational personnel for the new VVER-1200 power units.

3 August 2018  THE INFORMATION AND PR DEPARTMENT OF THE BELOYARSK NPP
“The decision to build the first of a kind BN-1200 power unit can be made in 2021”, the head of Rosenergoatom Andrey Petrov
“The decision to build the first of a kind BN-1200 power unit can be made in 2021”, the head of Rosenergoatom Andrey Petrov
The decision on the construction of the power unit No 5 of Beloyarsk NPP with the BN-1200 reactor can be made in 2021. This was announced by Andrey Petrov, the Director General of Rosenergoatom JSC (a part of the Rosatom Electric Power Division), during the Director's Day Briefing that took place at Beloyarsk NPP on 2 August, 2018.