08.11.2012  Communications Department of JSC Atomenergoproyekt

Novovoronezh II Begins Concreting of 4-5 Containment Tier of Unit 2 Reactor Building

Concreting of the combined fourth-fifth tier (from the level +34.42 to the level +44.10 m) of the inside containment (IC) of Unit 2 reactor building started at Novovoronezh II (general designer and contractor Р JSC Atomenergoproyekt, Moscow).
In construction of the reactor building containment of Unit 2, there is implemented a pilot project of Rosatom Production System (RPS). The project ТManufacturing, Assemblage of Reinforced Concrete Blocks and Concreting of the Inside ContainmentУ is aimed at loss reduction and optimization of production. As a result, the project has already managed to reduce terms and improve the quality of works.

Completion of the installation of the cylindrical part of the reactor building containment is scheduled for December. At the moment, pre-assembly of metalwork of the inner containment dome of Unit 2 is underway at the site of Novovoronezh II.
 
The project AES-2006, whereby Novovoronezh II is in process of construction, provides for double reinforced-concrete containment of reactor. It prevents from leakage of radioactivity into the environment and serves as physical protection against natural and man-made external effects. The thickness of the inside and outer containments is, respectively, 1.2 and 0.5 m.

 JSC Atomenergoproyekt (www.aep.ru) is an enterprise of Rosatom State-owned Corporation (www.rosatom.ru), engineering company, general designer and general contractor of nuclear power plants. The company has designed the projects of the majority of NPPs on the territory of Russia, Eastern Europe and CIS countries. JSC Atomenergoproyekt is a general designer of Bushehr NPP in Iran, Kudankulam NPP in India and Akkuyu NPP in Turkey. Atomenergoproyekt is a general designer and general contractor of Novovoronezh II (two power units with VVER-1200 model reactors based on AES-2006). According to the decision of Rosatom State-owned Corporation, on the basis of JSC Atomenergoproyekt, there was created a management company. The management of JSC AEP includes: JSC NIKIMT-Atomstroy, JSC Energospetsmontazh, JSC VNIPIET, OJSC NPK Dedal, JSC SSMU Lenatomenergostroy, JSC SPb NIII EIZ, JSC Sibirskiy Orgstroyproyekt, JSC SMM and JSC Mosspetsatomenergomontazh. 