13 September 2023  INFORMATION AND PUBLIC RELATIONS DEPARTMENT OF LENINGRAD NPP
At the construction site of the Leningrad NPP, a foundation pit is ready for the construction of the reactor building of the new PWR-1200 power unit No. 7
At the construction site of the Leningrad NPP, a foundation pit is ready for the construction of the reactor building of the new PWR-1200 power unit No. 7
At the construction site of the Leningrad NPP, the main excavation work has been completed to develop a pit for the nuclear island of power unit No. 7 of PWR-1200
4 September 2023  COMMUNIKATIONS DEPARTAMENT OF ROSENERGOATOM
The work of Russian nuclear power plants for eight months made it possible to prevent emissions of about 70 million tons of greenhouse gases into the atmosphere
The work of Russian nuclear power plants for eight months made it possible to prevent emissions of about 70 million tons of greenhouse gases into the atmosphere
Russian nuclear power plants (branches of Rosenergoatom, Electric Power Division of Rosatom State Corporation) generated over 141.8 billion kilowatt-hours or 102.03% of the balance task of the Federal Antimonopoly Service (FAS) of Russia in eight months of 2023
29 August 2023  INFORMATION AND PUBLIC RELATIONS DEPARTMENT OF THE KURSK NPP
Concreting of the dome of the outer containment of power unit No. 1 was completed at the construction site of the Kursk NPP-2
Concreting of the dome of the outer containment of power unit No. 1 was completed at the construction site of the Kursk NPP-2
The outer containment (OC) is one of the physical barriers that protect the reactor plant from extreme external influences, which is a reinforced concrete structure
29 August 2023  INFORMATION AND PUBLIC RELATIONS DEPARTMENT OF BELOYARSK NPP
Steam generators of power unit No. 3 of the Beloyarsk NPP are being modernized to extend the service life until 2040
Steam generators of power unit No. 3 of the Beloyarsk NPP are being modernized to extend the service life until 2040
On August 24, power unit No. 3 with a BN-600 fast neutron reactor at the Beloyarsk NPP was taken out of service for scheduled preventive repair in order to carry out fuel refueling, and preventive maintenance of the main equipment. The main work will be the replacement of eight evaporative modules of steam generators
29 August 2023  INFORMATION AND PUBLIC RELATIONS DEPARTMENT OF ROSTOV NPP
The Rostov NPP: modernization of the cooling system made it possible not to reduce the capacity of power unit No. 3 during the summer maximum temperatures
The Rostov NPP: modernization of the cooling system made it possible not to reduce the capacity of power unit No. 3 during the summer maximum temperatures
Since the beginning of summer, power unit No. 3 of the Rostov NPP, operating with the support of fan cooling towers, has not been allowed to reduce power due to high air temperatures. The unit operates without restrictions, providing planned electricity generation for consumers in the South of Russia
24 August 2023  Information and Public Relations Department of the Kursk NPP
Two reactors of the Leningrad NPP have been completely unloaded of nuclear fuel
Two reactors of the Leningrad NPP have been completely unloaded of nuclear fuel
One of the important stages of preparation for the decommissioning of shut down power units No.
17 August 2023  Information and Public Relations Department of the Kursk NPP
At the building site of the Kursk NPP-2, the construction of a cold water outlet channel for the cooling tower of power unit No. 1 was completed
14 August 2023  Communications Department of ROSATOM
ESG-II (b) rating from Expert RA agency was assigned to ROSATOM
ESG-II (b) rating from Expert RA agency was assigned to ROSATOM
Rating agency Expert RA, JCS assigned ESG-II (b) rating to ROSATOM which conforms to very high level of compliance with the interests in the field of sustainable development when making key decisions
4 August 2023  INFORMATION AND PUBLIC RELATIONS DEPARTMENT OF LENINGRAD NPP
African journalists were told about the safety of PWR-1200 power units at the Leningrad Nuclear Power Plant
African journalists were told about the safety of PWR-1200 power units at the Leningrad Nuclear Power Plant
25 journalists from Tanzania, Nigeria, Kenya, Zambia, Ghana, South Africa, Senegal and Burundi visited the Leningrad NPP as part of the Russia-Africa 2023 summit. The leading African media representatives met with the Leningrad NPP management and went on excursions. Alexander Belyaev, Chief Engineer of LNPP-2, spoke about how the safety of the station's activities is ensured
3 August 2023  Communications Division of Rosatom Engineering Division
Reactor vessel for Tianwan NPP Unit 7 has arrived at the construction site in China
Reactor vessel for Tianwan NPP Unit 7 has arrived at the construction site in China
The reactor vessel for Unit 7 of Tianwan NPP, which is being constructed in China with the participation of Rosatom State Corporation Engineering Division, arrived at the construction site after covering the sea route from Russia in less than two months.